Ground floor progress

The race is on to finish the down stairs of the weaving barn for Susie's 60th birthday part on Feb 21. The plasterboarding is almost finished as are the elctrics and plumbing. The WC arrives next week and Ian Smith is going to skim the ceilings and walls in the front room in a couple of weeks - the rest of the walls I ll tape and joint, with thestone walls being chaux chanvred (lime and hemp rendered) by me once the plastering is finished.

front room ready for skimming



The back room which we'll use for washing the fleeces still needs to be tiled

WC and hot water tank








 